Making Bristol better for cycling

What’s going on?

Here is a list of everything we know of cycling-wise in Bristol. We need your help to keep it up to date so please let us know of anything else that you hear of.

If you are interested in any of these things or have new information on any of these things, please let us know via [email protected]

 

 SCHEMECyclescape link/ initial documentationStatus (updated 240713)Programme
1Portway/ Lawrence Weston Preliminary DesignLSTF
2Hartcliffe Way @Imperial ParkImproved facilities in the Hengrove Area. Possibles ideas include a shared use facility on Airport Road which links to Callington Road and/or extension of the Cycle City Hartcliffe Way scheme to link in with Imperial ParkPreliminary Design (Halcrow)LSTF
3Callington Road & Airport Rd link to Whitchurch PathImproved facilities in the Hengrove Area. Possibles ideas include a shared use facility on Airport Road which links to Callington Road and/or extension of the Cycle City Hartcliffe Way scheme to link in with Imperial ParkPreliminary Design (Halcrow)LSTF
4Wedmore Vale Yellow Route Combining with 20mph roll-out.LSTF/ 20
5Brunel Miledetails on Cyclescape LEZ?/ Redcliffe
6Redcliffe Hilldetails on CyclescapePrelim DesignLSTF/ METRO
7Bedminster Bridges Prelim Design. May need a temp LST scheme ahead of full Metro scheme.LSTF/ METRO
8Easton Waydetails on cyclescapeDetail DesignLSTF
9Cross City 1 – Clarence Rddetails on cyclescape LSTF
10Cross City 2 – Commercial Road   
11Bond Street/Temple Street/Temple Gate  LEZ
12Coronation Road  N/A
13Park Row – Malborough Street (Scope route)details on Cyclescape4/7/13 Contractors to do Feasibility Study only.LSTF
14Park Street  N/A
15Baldwin Street (Castle Park to Centre) 4/7/13 Contractor due to be appointedSafety Scheme Grant
16Bond Street South Crossing Prelim DesignLSTF
17Millennium Mile/ Harbourside Design OnlyLSTF
18Wilder Street surfacingResurface. Investigate delivering a ‘cycle street’ – may prove too expensiveDetailed DesignLSTF
19Post office site (Enterprise Zone)  LEZ
20Cycle Parking expansion Ongoing – still opportunitiesLSTF
21CPO – Callington Rd link  LEZ
22CPO VOSA land to widen BBRPdetails on cyclescapePrelim Designs doneLSTF
23CPO Industrial estate BBRPdetails on cyclescapeDesign OnlyLSTF
24St Philips St/Midland Rd crossingdetails on cyclescapePrelim DesignLSTF
25Barrow Road bollards and other iremsBollards will be done once resurfacing completePending 
26Newton Park link (Newtown?)details on cyclescapeComlete but some surface issuesLSTF
27Sign orbitals/yellow route Awaiting City Design and Network definition 
28Signing City Centre for cyclists Awaiting City Design and Network definition 
29Old Marketdetails on cyclescapePrelim designLSTF
30Beaufort RoadReduction of traffic speed
and volume and/or delivery of cycle facilities. 
As per neighbourhood partnmership priorities.
Prelim designHighways
31Broom Hill, StapletonInvestigate options to improve mini roundabout at the junction with Frenchay Park Road. Identified in CRISPInceptionLSTF
32Pill PathResurface path in partnership with North Somerset. Investigate only. LSTF
33Gloucester Road 4/7/13 Contractor due to be appointedSafety Scheme Grant
34Gloucester Road A38 Cycle Safety Schemes (S.Glos)details at South GlosConsultation closes 29 Jul 2013. The results will be published by 12 Aug 2013.Safety Scheme Grant
35Promenade Route – various parts  LSTF /LEZ
36Merchants Road crossing   
37Southmead Hospital   
38Clifton Suspension Bridge   
39A369 Portishead route   
40Lamb Street   
41The Downs   
42Downs Bridge   
43BRT2 Ashton Vale to Temple Meads   
44SBL – South Bristol Link   
45Park Street re-pavingOnly replacing what’s there. No dropped kerbs because it encourages vehicles to mount the pavement.  
46Narrow Quay – pedestrianisation   
 Staplehill Road resurfacingresurfacing programme being undertaken and we have an opportunity to change the lining  
48Baldwin Street Cycle Safety Fund schemeaddress the large number of crashes involving cycles on Baldwin St, at the junction with Queen Charlotte StreetDetailed design, consultation from 30 Aug 2013—10 Sep 2013 
49Strategic Cycling Network   
50Bristol Cycling Strategy   
51Bristol Cycling Design GuideInitial doc https://docs.google.com/document/d/1g1gvyoDQSYjmkSOszzXMMq3F165Eq78flZoL0QNEiyc/edit?usp=sharing  
52Stoke Road parking restrictionsFirst Bus redirected the No 40 away from Julian Road. It’s being restored, but after changes to parking on Stoke Road (source: signs on bus stops on Julian Road)