SCHEME | Cyclescape link/ initial documentation | Status (updated 240713) | Programme | |
1 | Portway/ Lawrence Weston | Preliminary Design | LSTF | |
2 | Hartcliffe Way @Imperial Park | Improved facilities in the Hengrove Area. Possibles ideas include a shared use facility on Airport Road which links to Callington Road and/or extension of the Cycle City Hartcliffe Way scheme to link in with Imperial Park | Preliminary Design (Halcrow) | LSTF |
3 | Callington Road & Airport Rd link to Whitchurch Path | Improved facilities in the Hengrove Area. Possibles ideas include a shared use facility on Airport Road which links to Callington Road and/or extension of the Cycle City Hartcliffe Way scheme to link in with Imperial Park | Preliminary Design (Halcrow) | LSTF |
4 | Wedmore Vale Yellow Route | Combining with 20mph roll-out. | LSTF/ 20 | |
5 | Brunel Mile | details on Cyclescape | LEZ?/ Redcliffe | |
6 | Redcliffe Hill | details on Cyclescape | Prelim Design | LSTF/ METRO |
7 | Bedminster Bridges | Prelim Design. May need a temp LST scheme ahead of full Metro scheme. | LSTF/ METRO | |
8 | Easton Way | details on cyclescape | Detail Design | LSTF |
9 | Cross City 1 – Clarence Rd | details on cyclescape | LSTF | |
10 | Cross City 2 – Commercial Road | |||
11 | Bond Street/Temple Street/Temple Gate | LEZ | ||
12 | Coronation Road | N/A | ||
13 | Park Row – Malborough Street (Scope route) | details on Cyclescape | 4/7/13 Contractors to do Feasibility Study only. | LSTF |
14 | Park Street | N/A | ||
15 | Baldwin Street (Castle Park to Centre) | 4/7/13 Contractor due to be appointed | Safety Scheme Grant | |
16 | Bond Street South Crossing | Prelim Design | LSTF | |
17 | Millennium Mile/ Harbourside | Design Only | LSTF | |
18 | Wilder Street surfacing | Resurface. Investigate delivering a ‘cycle street’ – may prove too expensive | Detailed Design | LSTF |
19 | Post office site (Enterprise Zone) | LEZ | ||
20 | Cycle Parking expansion | Ongoing – still opportunities | LSTF | |
21 | CPO – Callington Rd link | LEZ | ||
22 | CPO VOSA land to widen BBRP | details on cyclescape | Prelim Designs done | LSTF |
23 | CPO Industrial estate BBRP | details on cyclescape | Design Only | LSTF |
24 | St Philips St/Midland Rd crossing | details on cyclescape | Prelim Design | LSTF |
25 | Barrow Road bollards and other irems | Bollards will be done once resurfacing complete | Pending | |
26 | Newton Park link (Newtown?) | details on cyclescape | Comlete but some surface issues | LSTF |
27 | Sign orbitals/yellow route | Awaiting City Design and Network definition | ||
28 | Signing City Centre for cyclists | Awaiting City Design and Network definition | ||
29 | Old Market | details on cyclescape | Prelim design | LSTF |
30 | Beaufort Road | Reduction of traffic speed and volume and/or delivery of cycle facilities. As per neighbourhood partnmership priorities. | Prelim design | Highways |
31 | Broom Hill, Stapleton | Investigate options to improve mini roundabout at the junction with Frenchay Park Road. Identified in CRISP | Inception | LSTF |
32 | Pill Path | Resurface path in partnership with North Somerset. Investigate only. | LSTF | |
33 | Gloucester Road | 4/7/13 Contractor due to be appointed | Safety Scheme Grant | |
34 | Gloucester Road A38 Cycle Safety Schemes (S.Glos) | details at South Glos | Consultation closes 29 Jul 2013. The results will be published by 12 Aug 2013. | Safety Scheme Grant |
35 | Promenade Route – various parts | LSTF /LEZ | ||
36 | Merchants Road crossing | |||
37 | Southmead Hospital | |||
38 | Clifton Suspension Bridge | |||
39 | A369 Portishead route | |||
40 | Lamb Street | |||
41 | The Downs | |||
42 | Downs Bridge | |||
43 | BRT2 Ashton Vale to Temple Meads | |||
44 | SBL – South Bristol Link | |||
45 | Park Street re-paving | Only replacing what’s there. No dropped kerbs because it encourages vehicles to mount the pavement. | ||
46 | Narrow Quay – pedestrianisation | |||
Staplehill Road resurfacing | resurfacing programme being undertaken and we have an opportunity to change the lining | |||
48 | Baldwin Street Cycle Safety Fund scheme | address the large number of crashes involving cycles on Baldwin St, at the junction with Queen Charlotte Street | Detailed design, consultation from 30 Aug 2013—10 Sep 2013 | |
49 | Strategic Cycling Network | |||
50 | Bristol Cycling Strategy | |||
51 | Bristol Cycling Design Guide | Initial doc https://docs.google.com/document/d/1g1gvyoDQSYjmkSOszzXMMq3F165Eq78flZoL0QNEiyc/edit?usp=sharing | ||
52 | Stoke Road parking restrictions | First Bus redirected the No 40 away from Julian Road. It’s being restored, but after changes to parking on Stoke Road (source: signs on bus stops on Julian Road) |